Before You Price a Cabinet Repaint, Count More Than Doors
A completed $2,200 cabinet repaint shows why counting doors is only the beginning of a useful estimate.
PropertyPromoKit team · November 7, 2026 · AI-assisted article based on owner-confirmed Yerg Remodeling job details. Bryan Yerg owns both businesses.

Start with the job we can actually document
Yerg Remodeling completed a bathroom cabinet repaint for $2,200. The recorded scope included a vanity with four doors and four center drawers, exposed frames, and an over-toilet cabinet. Surface preparation, primer, finish and cleanup were included. PropertyPromoKit’s public example recreates that work using owner-confirmed figures, with customer contact details removed.
That total is a historical example, not a price sheet. It does not establish a per-door rate, a local market average or what another contractor should charge. The published scope also does not establish the original finish, product system, hours worked, number of coats or every site condition. Those unknowns matter. The useful exercise is to use this compact job to build a repeatable review before pricing the next one.
1. Count surfaces, then count the handling
“Four doors and four drawers” sounds like eight items. It is not a complete description of the surfaces or work. For a new estimate, record whether door fronts, backs and edges are included. Distinguish drawer fronts from drawer boxes and interiors. Note exposed cabinet ends, face frames, toe kicks and any separate cabinet above the toilet. Measure where dimensions affect materials or labor.
Next, record how those parts will be handled. Will doors and fronts stay in place, or will they be removed? Who labels, stores and reinstalls them? Are hinges, pulls and bumpers staying, being replaced or supplied by the customer? These are questions for the next job, not claims about how the $2,200 project was performed. A count becomes useful only when everyone agrees what each counted item includes.
2. Treat preparation as a scope decision
Before selecting a coating system or committing to a finish, inspect the existing surfaces and follow the selected manufacturers’ preparation and application instructions. Record visible damage, contamination, peeling, previous repairs and uncertainty about the existing finish. A photo can document what is visible; it cannot prove compatibility, adhesion or hidden condition.
Separate ordinary preparation from additional repairs. For example, cleaning and preparing sound surfaces is different from repairing damaged panels or removing a failing coating. Describe what you have allowed for and what requires inspection or a separate price. Do not silently absorb a different preparation job into the same vague line. Equally, do not promise a preparation method before checking whether it fits the actual substrate and product system.
3. Price the occupied room, not just the cabinet
A bathroom cabinet sits inside somebody’s home. Protection, access and cleanup are part of delivering the work. Ask which nearby surfaces need protection, where parts can be staged and whether the customer needs the room during the work. Confirm whether belongings will be removed before arrival and who handles that task. Record any limitations that affect setup or daily access.
The small-job trap is treating this work as incidental because the visible cabinet is small. Setup and cleanup still consume crew time. Include the tasks that apply to your job in the internal plan, even when the customer sees one package price. That helps you explain what the package covers without turning the proposal into an internal time sheet.
4. Separate elapsed days from working hours
A project can span several calendar days without requiring a full crew on site every day. Product instructions, drying or curing requirements, access windows and return visits affect the plan differently. For a new quote, list the work on each visit and estimate the crew time needed for that work. Keep travel and remobilization in view when they create real costs.
Then explain the customer-facing schedule in plain language. Avoid promising that the room or cabinets will be ready for normal use at the same moment application ends. Confirm the applicable product requirements and handover instructions. The historical $2,200 price does not tell us the original project’s schedule; use your own completed-job records to check whether your next plan is realistic.
5. Keep the package price separate from the cost check
A customer can receive a clear total while the contractor keeps a detailed internal budget. Build that budget from the actual tasks, crew costs, materials, consumables and other direct expenses that apply. Review overhead separately when deciding whether the price supports the business. Do not interpret a selling price as proof of profit.
For a purely hypothetical calculation, $1,000 of direct cost with a 50% markup produces a $1,500 selling price. The $500 difference is a 33.3% gross margin before overhead and other uncounted expenses. It is not a 50% margin. These round numbers do not describe the Yerg cabinet job. The distinction matters because a contractor who mixes up markup and margin can approve a price that fails their own target.
6. Make “while you’re here” a visible decision
An extra shelf, new hardware or another cabinet may be reasonable work to add. The problem is leaving its status uncertain. Write down the added task, inspect what it involves and decide whether it changes materials, labor, customer price or timing. Explain those effects and obtain the customer’s agreement through your normal process before starting the added work.
Keep the original scope and the added work together so the final invoice can be reconciled with what was agreed. A single package total does not prevent clear scope boundaries. On the contrary, the fewer prices a customer sees, the more useful it is to describe exactly what that package includes and which requested changes sit outside it.
Use the estimate as a learning record
After completion, compare the work you planned with the work you actually performed. Record actual labor and materials, return visits and the reasons for meaningful differences. If preparation took longer, identify the condition or missing question rather than merely increasing every future cabinet price. If the customer supplied hardware late, record the resulting extra visit. Specific observations improve the next estimate more than a blanket adjustment.
This is where software can help organize the evidence. PropertyPromoKit connects job notes, photos, editable estimates and entered costs; a notebook or spreadsheet can support the same review discipline. AI can help structure a draft, but it cannot supply an inspection that never happened. Before sending any quote, verify the surfaces, preparation, quantities, prices and boundaries yourself. The aim is a scope you can deliver and learn from—not a number copied from somebody else’s job.
Use the guide on your next small job
Write down surfaces, preparation, protection, handling, visit plan, costs and exclusions before settling the price. Review the customer version on a phone before sending.
Ready to try PPK? Keep one saved project free, with no card required.